The CSAH 30 project in Delano is nearing completion. The project contractor is completing the aggregate base work on the west end of the project, as well as near the intersection of CSAH 30 and McKinley Parkway. Following the completion of the aggregate base work, the contractor will be installing light fixtures near the intersections of CSAH 13 and McKinley Parkway along CSAH 30. There is also work being done to shape the ditches along CSAH 30 to bring them up to design grade. Once the aggregate base for the project has been completed, CSAH 30 will open to local traffic, but the west end of the project (west of the CSAH 13 intersection) will remain closed until the aggregate base work is completed.