Highway Department Has Update on CSAH 30 Project in Delano

A message from Virgil Hawkins, Wright County Highway Engineer

Work on Highway 30 is on track to be completed for the season by mid-October (weather permitting). The Highway 30 Project is a collaborative effort between the county and city with both agencies sharing in the cost of the improvements. The project is a City of Delano contract with construction administration and inspection by the city's engineering firm, Wenck, Inc. of Maple Plain, MN. The prime contractor for this project is GMH Asphalt Corporation out of Chaska, MN. A traffic detour has been in place since May for this section of highway 30. Local traffic for those who live along this portion of CSAH 30 will be coordinated and maintained during construction.

Remaining work that is scheduled to be completed in the next couple of weeks (by mid-October, 2020) includes, but is not limited to the following:  

  • Concrete flat-work

  • Class 5 aggregate base fine grading (in preparation for paving)

  • Placement of asphalt bituminous base course 

  • Painting temporary pavement markings

  • Installation of traffic signs

  • Removal of detour signing - open highway to traffic

  • Seeding/restoration & cleanup

    The final lift of bituminous pavement and final pavement markings will take place in 2021, with final completion by June 30, 2021. The project improvements include reconstructing and widening the 2-lane rural section and construct a roundabout at the intersection of CSAH 30 and McKinley Parkway/Davidson Avenue. Replacement of culvert crossings and additional storm sewer, as well as sanitary sewer and watermain utility extensions.

    Project information, such as contact list, detour route, the project schedule, or to get signed up for weekly updates is provided on the Delano City website at http://www.delano.mn.us/whats-new/construction-projects  If you need assistance getting signed up for the weekly updates, please contact Delano City Clerk Paula Bauman at pbauman@delano.mn.us.

    Questions or concerns regarding the project can be directed towards Shawn Louwagie, Delano City Engineer @ 763-479-4274 or by email at slouwagie@wenck.com. On behalf of Wright County and the City of Delano, we greatly appreciate your patience during the construction process.

     

Facebook Twitter Email

Other News in Wright County News

View the Ballot You Will Be Filling Out

Posted on: October 21, 2020

Buckthorn a Problem in Woodland Areas

Posted on: October 13, 2020

Tuesday is National Voter Registration Day

Posted on: September 18, 2020

Absentee Voting In Person Starts Friday

Posted on: September 14, 2020

CSAH 30 Project Nearing Completion

Posted on: September 8, 2020

Road Work on Hwy. 25 Starting Sept. 8

Posted on: September 3, 2020

Sirens to Sound at 1 P.M. Today, But Why?

Posted on: September 2, 2020

Road Closure in Monticello Tuesday

Posted on: August 24, 2020

Why Are Flags at Half-Mast Today?

Posted on: August 19, 2020

Where Is My Polling Place Location?

Posted on: August 10, 2020

Trailblazer Ridership on the Rise

Posted on: March 4, 2020

Husom Reflects on County Plans for 2020

Posted on: February 4, 2020

Confusion Remains Over New T-21 Law

Posted on: January 3, 2020

Long Range Transportation Plan Adoption

Posted on: October 14, 2019