The Wright County Highway Department has released a general timeline for the CSAH 39/Odean Avenue construction project in Otsego. Dates are subject to minor changes due to weather conditions.
Remainder of this week – re-spreading of topsoil, preparing concrete media and for curbing on the north side of CSAH and Odean.
Week of June 21 – Pouring concrete media and north curb on Odean roundabout.
Week of June 28 – Placement of ADA ramps, intersection work and completion of pedestrian ramps
Week of July 5 – Paving base and binder work
Week of July 12 – Pave wear course
Week of July 19 – Permanent striping and signage.
The project is expected to be completed by the end of July.