The Wright County Highway Department has released a tentative time schedule for the County Road 118 (Fenning Avenue) roundabout project. All the dates and time duration for the different portions of the project are weather-dependent.
Subgrade Preparation – (12 workdays) Thursday July 15 through Friday July 30
Place Select Granular – (9 days) Monday, July 19 through Thursday July 29
Storm Sewer in Front of Wall – (2 days) Thursday, July 15 through Friday, July 16
Finish Grading/Base Temporary Bypass – (2 days) Friday, June 16 though Monday, June 19
Pave Temporary Bypass – (4 days) Tuesday, July 27 through Friday, July 30
Close Roundabout/Place Traffic on Bypass – (1 day) Monday, Aug. 2
Removals in Roundabout – (2 days) Monday Aug. 2 through Tuesday, Aug. 3
Underground in Roundabout – (11 days) Tuesday, Aug. 3 through Tuesday, Aug. 17
Grade Roundabout – (5 days) Tuesday, Aug. 17 to Monday, (Aug. 23)
Construction on the project is being done by Duininck, Inc. of Monticello.