The Minnesota Department of Transportation has announced that there will be short-term lane closures on I-94 on eastbound I-94 between Co. Rd. 8 in Hasty and Hwy. 25 in Monticello. Traffic will be reduced to a single lane at various times for the installation of High Tension Cable Barriers.
The allowable lane closure hours are between 9 p.m. and 11 a.m. Sundays, 6 p.m. to 11 a.m. Mondays through Wednesdays, 6 p.m. to 11 a.m. Thursdays and 7 p.m. to 10 a.m. Fridays. The work is scheduled to run from Tuesday, June 14 and end Thursday, July 1.