A Message from the Wright County Highway Department:
Work continues on the CSAH 83/Co. Rd. 148 (Braddock Avenue NE) roundabout and Co. Rd. 148 realignment project north of Buffalo near the Wright County Government Campus. This project is expected to be open to traffic by the end of October or early November (weather permitting).
During the remaining construction work, CSAH 83 will remain closed, and traffic will be detoured as currently signed. Co. Rd. 148 (Braddock Avenue NE) will be closed to all traffic from the intersection of CSAH 83 north to just before the entrance to the Wright County Government Center. Traffic will be directed to follow a posted detour route to access the Government Center, Justice Center, Law Enforcement Center, and County Jail utilizing Co. Rd. 113 off Hwy. 25.
We encourage traffic to use the “Alternate Route” when navigating to the north leaving the Government Center Campus.
Some of the remaining work and schedule is as follows:
- Curb and gutter installation next week (Oct. 17th -20th)
- Paving the week of Oct. 23rd
- Retaining wall installation after curb has been installed.
- Open to traffic by the end of October/early November (weather permitting)
Please contact the Wright County Highway Department at 763-682-7383 if you have questions about this important safety improvement project.