A Message from the Wright County Highway Department:
The contractor on the Braddock Avenue NE roundabout project that has detoured traffic to county facilities has provided a schedule as of 8 a.m. today (Oct. 27):
Curb and Gutter – completed Oct. 24
Lighting – bases installed, poles installed the week of Oct. 30
Paving – Oct. 30 to Nov. 2
Flatwork (concrete medians) and ADA pedestrian ramps – Nov. 6-10
Topsoil – Nov. 10-14
Signing – Nov. 14-15
Substantial completion (open to traffic) – Nov. 15